Qué debe hacer
1. Submit the addenda schedule, if necessary
Site Permit applicants submitting multiple addenda must first submit their addenda schedule request for approval to dbi.ppcrequest@sfgov.org. Subsequent addenda are to be submitted using the building permit application portal and must include the approved addenda schedule.
2. Create PDFs of your original submittal package plans and all plans for this addenda submission
Follow these rules to create PDFs of plans.
PDFs must be editable. Do not submit locked, password-protected, encrypted, or “restricted” documents.
Each upload must be less than 250 MB.
Title blocks must have your project address, sheet count, and sheet name.
Every sheet must have your signature and stamp. Use a scanned graphic signature with a PDF stamp.
Incomplete submissions may delay the processing of your application.
3. Add our Back Check Page
You must add our Back Check Page PDF to submit plans in Bluebeam, our electronic plan review software.
4. Download and fill out the Addenda PDF
Fill out the addenda PDF with your job address, permit number, and relevant information.
5. Submit construction addenda using the building permit application portal
You will need to include:
- Addenda form
- Addenda drawings
- Project address
- Approved site permit application number
- Copy of approved site permit application
- Copy of approved site permit drawings
- Associated nine-digit Bluebeam project ID number
- Approved addenda schedule (if applicable)
- Addenda number for this submission (if applicable)
6. Follow-up
The City will review your construction addenda submission and contact you if revisions or additional information is required.
We will notify you when our review is complete.