Expanded Compliance Control Program

May 22, 2024

Back to top

About the program

The Expanded Compliance Control Program (ECC) was created in 2021 as a way to ensure that contractors, design professionals, building owners, and their agents fully comply with the City of San Francisco’s Building Code.

The Expanded Compliance Control program requires the Department of Building Inspection to track significant violations and all parties associated with such violations, review those tracking reports to identify candidates for expanded compliance control measures and, when appropriate, place them on the Expanded Compliance Control List.

San Francisco Building Code Section 103A.6 mandates that the Department perform the following Expanded Compliance Control measures for each individual placed on the Expanded Compliance Control List:

  • Provide the Director’s final determination and findings to any applicable licensing board or regulatory agency (if any)
  • Require all new or existing permits or addenda submitted by, or containing reference to, a listee undergo Expanded Compliance Control by senior Plan Review Services staff and review at intake by applicable departments
  • Notify the listee and all other parties associated with the listee on a permit application or addenda of the Expanded Compliance Control requirements
  • Require a licensed contractor be named on a permit
  • Require site inspection by DBI and the Planning Department prior to permit issuance for projects associated with the listee
  • Dedicate a senior inspector to respond to complaints and conduct all inspections regarding the listee
  • Consult with City Attorney, if warranted, about any other enforcement options
Back to top

Why is this program in place?

Significant violations of the Building Code threaten public health and safety; require DBI time and resources to identify, enforce, and abate; and often result in costly litigation and delay in repairing or constructing much needed housing throughout the City.

For all parties—property owners/consumers, residents, DBI, and the public at large—it is safer, more cost-effective and efficient to adopt expanded compliance control provisions that ensure compliance throughout the permit review process, rather than address violations after the fact through enforcement proceedings.

Back to top

Expanded Compliance Control List

The following individuals and/or entities are subject to Expanded Compliance Control Measures.  They will remain on the list for a period of five years, provided they are not found to be responsible for subsequent Building Code Violations.

Name and Notice of DeterminationDate placed on list

John Pollard (S.F. Garage Company, Inc.)

Harold Howell*

Ginny Santos

Tad Van Nguyen

Rodrigo Santos

04/01/2024

04/01/2024

02/13/2024

12/26/2023

11/18/2021

*Determination under appeal

 

Back to top