Anong gagawin
All single-walled Underground Storage Tanks must be permanently closed by December 31, 2025. Learn more in Senate Bill 445.
1. Contact us to apply
To get a permit to modify, repair, or install a tank, contact us.
We'll work with you on what you need to include in your permit application.
Have documentation ready
Depending on the project, you might need to include:
- Plans of the facility and underground storage tank system
Including a list of specifications for all materials used in the construction.
- Manufacturers’ cut sheets for tanks, piping and equipment
Like the monitoring equipment, overspill containment device, overfill protection device, and dispenser pan.
- Copy of current state contractor’s license
For example: A, C-36, C-61 D-40
- Copy of certifications
ICC and Manufacturers’ certifications for all installers and technicians
We generally process complete applications within 10 working days.
2. Pay the fee
Write a check, cashier’s check, or money order to “San Francisco Department of Public Health”. Check the fee schedule for the exact amount. Mail the fee to:
Environmental Health
Attention: Hazardous Materials and Waste49 South Van Ness Avenue
Suite 600
San Francisco, CA 94103
Please note the current UST Installation/Modification fees for Fiscal Year 2024-2025 beginning July 1, 2024:
Work involving excavation and/or cutting of concrete: $1,390
Work not involving excavation and/or cutting of concrete: $765
Espesyal na mga kaso
You might need other permits
You might need other permits
As part of the process, you may be directed to work with the following City agencies:
San Francisco Fire Department
- 415-558-3300
- Fire department permits
Department of Public Works
- 415-554-5810
- Street-use and mapping
Bay Area Air Quality Management District
- 415-771-6000
- Underground tank permits
Department of Building Inspection
- 415-558-6088
- Building permit services
San Francisco Planning
- 415-558-6377
- SF Planning